Kitchen Remodel Order: Cabinets, Flooring, Countertops

The typical sequence of a kitchen remodel, from decisions and demolition to cabinets, flooring, countertops and finishing.

White shaker upper cabinets above charcoal base cabinets and a grey island during installation

The Short Answer

A typical sequence is: finalize decisions, demolition, rough plumbing and electrical, flooring (when it runs under cabinets), cabinet installation, countertop templating and installation, then backsplash, fixtures and final adjustments.

Step-by-Step Kitchen Remodel Sequence

  • 1. Finalize layout, cabinets, appliances, countertop and flooring
  • 2. Demolition and removal
  • 3. Rough plumbing and electrical changes
  • 4. Drywall repairs and paint prep
  • 5. Flooring (if it runs under cabinets)
  • 6. Cabinet installation, levelled and scribed
  • 7. Countertop templating off installed cabinets
  • 8. Countertop installation
  • 9. Backsplash, sink, fixtures and appliances
  • 10. Door and drawer adjustments and walkthrough

Why Decisions Come Before Demolition

Appliance sizes, sink location and countertop material all affect cabinet dimensions. Choosing them first keeps the kitchen out of service for less time and avoids rework. Our checklist of what to decide before replacing kitchen cabinets covers the essentials.

Why Countertops Wait for Cabinets

Templating off installed, level cabinets ensures the top fits the room as built, including walls that are not perfectly straight. See quartz vs granite countertops for choosing the material.

Blue-grey glass-front upper cabinets with interior lighting above a white quartz counter
Countertops are measured off installed cabinets so they fit the finished room.

Where Flooring Fits

Some floors go in before cabinets and some after. It depends on the product; see should flooring go under kitchen cabinets.

Keeping the Project on Track

Fewer Handoffs

Each handoff between trades is a chance for delays. Coordinating cabinets, countertops and flooring together reduces them.

Plan for Living Without a Kitchen

Set up a temporary space for a microwave, coffee maker and fridge access during demolition and installation.

Planning a Kitchen Remodel?

Our kitchen remodeling page explains the scope we handle. Utah Cabinet Works designs, builds and installs cabinetry from our shop in West Jordan, and we serve homeowners across the Salt Lake Valley. You can see finished rooms in our project gallery and read more about how we work.

Straight answers

Common Questions

Blue-grey glass-front upper cabinets with interior lighting above a white quartz counter
Do cabinets or countertops go in first?
Cabinets. Countertops are measured off installed cabinets.
When should I order cabinets?
Once the layout and appliances are finalized, so dimensions are fixed.
Does paint go before or after cabinets?
Often walls are primed and painted before cabinets go in, with touch-ups at the end.